IITIAN1997 STUDIO

Why is the discharge isolation (gate) valve placed after the NRV on a pump?

Valves, piping & fittings · interview question with WHY and HOW

Ask your own question →

Short answer: Order from pump: NRV first, then the discharge isolation valve. This lets the NRV be removed for maintenance by closing the isolation valve while the header stays in service.

Why

If the isolation valve were next to the pump and the NRV beyond it, a leaking or stuck NRV could not be isolated from the header pressure for repair.

How

  1. Typical discharge line: pump → pressure gauge → NRV → gate valve → header.
  2. Minimum-flow recirculation line tees off before the NRV.
  3. Suction side: header → gate valve → strainer → pump.

What you learn only in industry

Some plants put the gate valve before the NRV; the reason above is why most standards and P&IDs put the NRV first — be ready to explain your plant’s choice.

Likely focus at

IOCL, HPCL, BPCL, NRL, MRPL, CPCL, ONGC, Oil India, GAIL, BCPL, EIL, NFL, RCF, BVFCL, NPCIL, Heavy Water Board. Organisation names show where a topic is a likely focus because of what the organisation does; they are not claims that a particular question was asked. Recruitment routes change each year, so confirm in the official notification.

Frequently asked questions

Why is the discharge isolation (gate) valve placed after the NRV on a pump?

Order from pump: NRV first, then the discharge isolation valve. This lets the NRV be removed for maintenance by closing the isolation valve while the header stays in service. Why: If the isolation valve were next to the pump and the NRV beyond it, a leaking or stuck NRV could not be isolated from the header pressure for repair.

Related questions

Ask your own question →