Short answer: A procedure to review and approve any change to process, equipment, chemicals, procedures or organisation before it is implemented.

Why

Small, unreviewed changes (a bypass, a new material, a different catalyst) have caused major accidents, e.g. Flixborough (1974) temporary pipe.

How

  1. Describe the change, hazards assessed (HAZOP-lite), approvals from disciplines.
  2. Update P&IDs, procedures and training.
  3. Pre-start-up safety review (PSSR) before commissioning.

Likely focus at

IOCL, HPCL, BPCL, NRL, MRPL, CPCL, ONGC, Oil India, GAIL, BCPL, EIL, NFL, RCF, BVFCL, BARC, NPCIL, Heavy Water Board, DRDO, ISRO. Organisation names show where a topic is a likely focus because of what the organisation does; they are not claims that a particular question was asked. Recruitment routes change each year, so confirm in the official notification.