Time value of money, capital and manufacturing cost estimation, depreciation, NPV and IRR, break-even, optimum design, linear programming and CPM/PERT.
What is inside
- Interest, annuities and cost indices
- Lang factor capital and depreciation
- NPV, IRR, payback and break-even
- Optimum pipe size, LP and CPM/PERT
Syllabus: ASTU HS241506 · CHE181822 (cost chapters) Process Engineering Economics & Optimization, semester 5 & 8, No single ASTU course: built from HS241506 and the Project-II cost-estimation chapter. Official syllabus PDF.
Time value of money
Topics: Simple and compound interest; nominal and effective rates; continuous compounding; present and future worth; annuities, sinking fund and capital recovery factors; capitalised cost.
Money now is worth more than money later. Future value F = P(1 + i)ⁿ; present value P = F/(1 + i)ⁿ. An annuity of A per year for n years has present value P = A[(1 + i)ⁿ − 1]/[i(1 + i)ⁿ]; its inverse, the capital recovery factor, turns a capital cost into an equal yearly charge. Effective rate for m compoundings per year: (1 + r/m)^m − 1; continuous: e^r − 1. Capitalised cost K = C_V + (C_R)/((1 + i)ⁿ − 1) funds a replacement forever.
- Compare alternatives at the same time point (present worth) or as equal annual cost.
- Higher interest rate favours lower first cost.
- Sinking fund factor = i/[(1 + i)ⁿ − 1].
- Capitalised cost compares equipment with different lives.
Key formulas
- F = P(1 + i)ⁿ
- P = A[(1 + i)ⁿ − 1]/[i(1 + i)ⁿ]
- CRF = i(1 + i)ⁿ/[(1 + i)ⁿ − 1]
- i_eff = (1 + r/m)^m − 1
- K = C_V + C_R/[(1 + i)ⁿ − 1]
Practice questions
₹1000 at 10 % compound for 2 years becomes
- ₹1200
- ₹1210
- ₹1100
- ₹1331
Show the answer
Answer: B. ₹1210 1000 × 1.21.
The capital recovery factor converts
- annual cost to present
- present cost to equal annual cost
- future to present
- nominal to effective
Show the answer
Answer: B. present cost to equal annual cost A = P × CRF.
12 % nominal compounded monthly has an effective rate of
- 12 %
- 12.68 %
- 13 %
- 11.4 %
Show the answer
Answer: B. 12.68 % 1.01¹² − 1.
Capitalised cost is used to compare equipment with
- the same life
- different lives
- no cost
- no salvage
Show the answer
Answer: B. different lives Perpetual service.
Theory questions
Pump A costs ₹2 lakh and lasts 5 years; pump B costs ₹3.5 lakh and lasts 10 years. At 10 %, which has the lower equivalent annual cost? (4 marks)
Show the model answer
CRF(10 %, 5) = 0.2638 ⇒ A: ₹52 760/yr. CRF(10 %, 10) = 0.1627 ⇒ B: ₹56 950/yr. Pump A is cheaper per year (ignoring running costs).
Define nominal and effective interest and derive the continuous-compounding limit. (3 marks)
Show the model answer
Nominal r is quoted per year; with m periods the effective rate is (1 + r/m)^m − 1. As m → ∞, (1 + r/m)^m → e^r, so i_eff = e^r − 1.
Capital cost estimation
Topics: Fixed capital and working capital; types of estimates (order-of-magnitude to definitive); cost indices (CEPCI); six-tenths rule and capacity exponents; equipment purchase-cost correlations; Lang factors; percentage-of-delivered-equipment method; total capital investment.
Total capital investment = fixed capital (equipment, installation, piping, instruments, buildings, engineering, contingency) + working capital (≈ 10–20 % of fixed capital). Costs move with time by a cost index: C₂ = C₁(I₂/I₁), using the CEPCI. Costs scale with capacity: C₂ = C₁(Q₂/Q₁)^n with n ≈ 0.6 for whole plants (six-tenths rule). A quick fixed-capital estimate multiplies delivered equipment cost by the Lang factor: 3.1 (solids), 3.6 (solid–fluid), 4.7 (fluid processing) in Peters’ basis, or ≈ 5 including all on-site costs.
- Estimate classes: order-of-magnitude (±30–50 %), study, preliminary, definitive, detailed (±5 %).
- CEPCI: 1957–59 = 100; recent years ≈ 800.
- Contingency 10–20 % of fixed capital.
- Delivered cost ≈ purchase × 1.1.
Key formulas
- C₂ = C₁ (I₂/I₁)
- C₂ = C₁ (Q₂/Q₁)^n, n ≈ 0.6
- FCI = f_L × Σ C_delivered
- TCI = FCI + WC
Practice questions
The six-tenths rule relates cost to
- time
- capacity
- temperature
- labour
Show the answer
Answer: B. capacity C ∝ Q^0.6.
The Lang factor for a fluid-processing plant (Peters) is about
- 1.5
- 3.1
- 4.7
- 10
Show the answer
Answer: C. 4.7 Fluid plants.
Working capital is roughly
- 1 %
- 10–20 % of FCI
- 100 % of FCI
- zero
Show the answer
Answer: B. 10–20 % of FCI Stocks, receivables, cash.
Updating a 2010 cost to 2025 uses a
- Lang factor
- cost index
- CRF
- Reynolds number
Show the answer
Answer: B. cost index CEPCI ratio.
Theory questions
A 50 000 t/yr plant cost ₹200 crore when CEPCI was 550. Estimate a 100 000 t/yr plant when CEPCI is 800. (4 marks)
Show the model answer
Capacity: 200 × 2^0.6 = 303.1; time: × 800/550 = ₹440.9 crore.
Delivered equipment for a fluid plant costs ₹50 crore. Estimate FCI and TCI. (3 marks)
Show the model answer
FCI = 4.7 × 50 = ₹235 crore; WC = 15 % ⇒ ₹35 crore; TCI ≈ ₹270 crore.
Manufacturing cost and depreciation
Topics: Direct production costs (raw materials, utilities, labour, maintenance, supplies, royalties); fixed charges (depreciation, taxes, insurance); plant overheads; general expenses; total product cost; depreciation: straight-line, declining-balance, sum-of-years-digits; taxes.
Total product cost = manufacturing cost (direct production + fixed charges + overheads) + general expenses (administration, distribution and selling, R&D). Raw materials often dominate (50–80 % for commodity chemicals). Depreciation is a non-cash cost that reduces tax: straight-line d = (V − V_s)/n; declining balance writes off a fixed fraction of book value each year; sum-of-years-digits gives larger early write-offs. Cash flow after tax = (revenue − cost excluding depreciation)(1 − t) + t × depreciation.
- Maintenance ≈ 2–10 % of FCI per year.
- Operating labour from operators per shift × shifts.
- Depreciation is not cash; it shields tax.
- Gross profit − tax = net profit.
Key formulas
- d_SL = (V − V_s)/n
- Declining balance: d_k = f × book value_(k−1)
- SYD: d_k = (n − k + 1)/[n(n + 1)/2] × (V − V_s)
- Cash flow = (S − C)(1 − t) + t d
Practice questions
Depreciation is
- a cash expense
- a non-cash expense
- income
- tax
Show the answer
Answer: B. a non-cash expense Book-keeping allocation.
Straight-line depreciation for ₹10 lakh, salvage ₹1 lakh, 9 years is
- ₹1 lakh/yr
- ₹1.11 lakh/yr
- ₹0.9 lakh/yr
- ₹10 lakh
Show the answer
Answer: A. ₹1 lakh/yr 9/9.
The largest cost item for commodity chemicals is usually
- labour
- raw materials
- royalties
- R&D
Show the answer
Answer: B. raw materials 50–80 %.
Sum-of-years-digits gives
- equal yearly write-off
- larger early write-off
- larger late write-off
- no write-off
Show the answer
Answer: B. larger early write-off Accelerated.
Theory questions
A plant has sales ₹100 crore, cash costs ₹70 crore, depreciation ₹10 crore and tax 30 %. Find net profit and cash flow. (3 marks)
Show the model answer
Taxable = 100 − 70 − 10 = 20; tax 6; net profit 14. Cash flow = 14 + 10 = ₹24 crore (= 30 × 0.7 + 0.3 × 10).
List the components of total product cost. (4 marks)
Show the model answer
Manufacturing cost: direct production (raw materials, utilities, operating labour, supervision, maintenance, supplies, lab charges, royalties), fixed charges (depreciation, local taxes, insurance, rent), plant overheads. General expenses: administration, distribution and selling, R&D.
Profitability analysis
Topics: Payback period; return on investment; net present value; discounted cash flow rate of return (IRR); profitability index; comparison of alternatives; incremental analysis; sensitivity.
Payback = fixed capital/annual cash flow (ignores time value). ROI = annual net profit/total investment. NPV = Σ CF_k/(1 + i)^k − investment; a project is acceptable when NPV > 0 at the company’s minimum acceptable rate. IRR (DCFRR) is the rate that makes NPV = 0, found by trial or bisection. Between alternatives, incremental analysis checks whether extra investment earns at least the minimum rate. Sensitivity plots show which price or cost moves NPV most.
- NPV > 0 ⇒ accept.
- IRR > hurdle rate ⇒ accept.
- Payback ignores cash after payback and time value.
- Mutually exclusive projects: choose on NPV or incremental IRR, not IRR alone.
Key formulas
- Payback = FCI/annual cash flow
- ROI = net profit/TCI
- NPV = Σ CF_k/(1 + i)^k − I₀
- IRR: Σ CF_k/(1 + r)^k = I₀
Practice questions
A project is acceptable if NPV is
- negative
- positive
- zero only
- undefined
Show the answer
Answer: B. positive Earns more than the discount rate.
IRR is the discount rate at which
- NPV is maximum
- NPV = 0
- payback = 1
- ROI = 0
Show the answer
Answer: B. NPV = 0 Definition.
Payback period ignores
- investment
- time value of money
- cash flow
- profit
Show the answer
Answer: B. time value of money Undiscounted.
Incremental analysis compares
- two projects’ extra investment and extra return
- only costs
- only sales
- taxes
Show the answer
Answer: A. two projects’ extra investment and extra return Is the extra worth it?
Theory questions
An investment of ₹100 lakh returns ₹30 lakh/year for 5 years. Find payback, NPV at 10 % and IRR. (5 marks)
Show the model answer
Payback = 3.33 years. PV factor (10 %, 5) = 3.791 ⇒ NPV = 113.7 − 100 = ₹13.7 lakh. IRR: factor = 3.333 ⇒ r ≈ 15.2 %.
Compare payback, ROI, NPV and IRR as profitability measures. (4 marks)
Show the model answer
Payback and ROI are simple but ignore time value; NPV gives absolute value created at a chosen rate; IRR gives a rate independent of the hurdle but can mislead between mutually exclusive projects or with sign-changing cash flows.
Break-even analysis and inventory
Topics: Fixed and variable costs; break-even point and margin of safety; cost–volume–profit; shutdown point; economic order quantity; ABC analysis.
With fixed cost F, variable cost v per unit and price p, profit is zero at the break-even quantity Q_BE = F/(p − v); (p − v) is the contribution per unit. Margin of safety = (actual − break-even)/actual. A plant should keep running in the short term as long as price covers variable cost (shutdown point). Inventory: the economic order quantity EOQ = √(2DS/H) balances ordering cost S per order against holding cost H per unit per year for annual demand D.
- Contribution margin = p − v.
- Raising price or cutting variable cost lowers break-even.
- ABC analysis: A items (≈ 10 % of items, 70 % of value) get tight control.
- Total inventory cost is flat near the EOQ.
Key formulas
- Q_BE = F/(p − v)
- Margin of safety = (Q − Q_BE)/Q
- EOQ = √(2DS/H)
- Total cost = DS/Q + HQ/2
Practice questions
Break-even quantity with F = ₹10 lakh, p = ₹100, v = ₹60 is
- 10 000
- 25 000
- 16 667
- 100 000
Show the answer
Answer: B. 25 000 10⁶/40.
EOQ increases when holding cost
- increases
- decreases
- is unchanged
- doubles demand
Show the answer
Answer: B. decreases EOQ ∝ 1/√H.
In the short run a plant should shut down if price is below
- total cost
- variable cost
- fixed cost
- zero
Show the answer
Answer: B. variable cost Shutdown point.
A items in ABC analysis are
- many, low value
- few, high value
- all equal
- obsolete
Show the answer
Answer: B. few, high value Pareto.
Theory questions
Annual demand 12 000 drums, order cost ₹500, holding ₹20 per drum per year. Find EOQ and orders per year. (3 marks)
Show the model answer
EOQ = √(2 × 12 000 × 500/20) = √600 000 = 775 drums; about 15.5 orders per year.
Draw and explain a break-even chart. (4 marks)
Show the model answer
Fixed-cost line horizontal; total-cost line from F with slope v; revenue line from origin with slope p. They cross at Q_BE; to the right is profit, to the left loss; the gap between actual output and Q_BE is the margin of safety.
Optimum design
Topics: Optimisation in design; objective functions; single-variable optimisation; optimum pipe diameter, optimum insulation thickness, optimum reflux ratio, optimum cooling-water flow; optimum production rate; multivariable problems.
Many design choices trade capital against operating cost: a thicker pipe costs more but needs less pumping power; thicker insulation costs more but saves heat; more reflux means fewer trays but larger reboiler and condenser duties. Write the total annual cost C(x) = capital charge(x) + operating cost(x), set dC/dx = 0 and check d²C/dx² > 0. Rules of thumb follow, e.g. optimum steel-pipe diameter D_opt ≈ 0.363 Q^0.45 ρ^0.13 (SI, turbulent; Peters) and optimum reflux ≈ 1.1–1.5 R_min.
- Total annual cost has a minimum where marginal capital = marginal saving.
- Annualise capital with CRF or a fixed charge factor.
- Optimum is often flat: small errors cost little.
- Check constraints (velocity limits, pressure drop).
Key formulas
- dC/dx = 0, d²C/dx² > 0
- D_opt ≈ 0.363 Q^0.45 ρ^0.13 (m, m³/s, kg/m³)
- Insulation: C = a·x + b/(x + c) ⇒ x_opt = √(b/a) − c
Practice questions
The optimum pipe diameter minimises
- pressure drop only
- pipe cost only
- sum of annual pipe and pumping costs
- velocity
Show the answer
Answer: C. sum of annual pipe and pumping costs Total annual cost.
At the optimum of a minimum-cost problem
- dC/dx < 0
- dC/dx = 0 and d²C/dx² > 0
- dC/dx > 0
- C = 0
Show the answer
Answer: B. dC/dx = 0 and d²C/dx² > 0 Stationary minimum.
Optimum reflux ratio is typically
- R_min
- 1.1–1.5 R_min
- 10 R_min
- total reflux
Show the answer
Answer: B. 1.1–1.5 R_min Rule of thumb.
Increasing insulation thickness
- raises heat loss
- raises capital, lowers heat loss
- lowers capital
- has no effect
Show the answer
Answer: B. raises capital, lowers heat loss Trade-off.
Theory questions
Find the optimum diameter for 0.05 m³/s of water (ρ = 1000). (3 marks)
Show the model answer
D = 0.363 × 0.05^0.45 × 1000^0.13 = 0.363 × 0.2596 × 2.454 = 0.231 m: choose an 8 or 10 inch schedule-40 pipe (velocity ≈ 1.2 m/s).
Annual cost of insulation is C = 20 000x + 300/(x + 0.02) (₹ per m of pipe, x in m). Find x_opt. (4 marks)
Show the model answer
dC/dx = 20 000 − 300/(x + 0.02)² = 0 ⇒ (x + 0.02)² = 0.015 ⇒ x + 0.02 = 0.1225 ⇒ x ≈ 0.10 m (100 mm). Check d²C/dx² = 600/(x + 0.02)³ > 0, so it is a minimum.
Optimisation methods
Topics: Unconstrained optimisation: analytical, search methods (golden section, Newton); constrained optimisation: Lagrange multipliers; linear programming: formulation, graphical and simplex methods; applications: product mix, blending, refinery planning.
Single-variable searches (golden section, Fibonacci) shrink an interval around a minimum without derivatives; Newton’s method uses f′ and f″. With equality constraints, Lagrange multipliers solve ∇f = λ∇g. Linear programming maximises a linear objective subject to linear constraints; the optimum lies at a corner of the feasible region (graphical method for two variables, simplex for many). Refinery blending and product-mix problems are classic LPs.
- Golden section reduces the interval by 0.618 each step.
- LP optimum is at a vertex of the feasible region.
- Shadow price: gain per extra unit of a scarce resource.
- Non-linear problems may have several local optima.
Key formulas
- Golden ratio τ = 0.618
- Newton: x_(k+1) = x_k − f′(x_k)/f″(x_k)
- Lagrange: ∇f = λ∇g
- LP: max cᵀx, Ax ≤ b, x ≥ 0
Practice questions
The LP optimum lies at
- the centre
- a vertex of the feasible region
- outside
- the origin always
Show the answer
Answer: B. a vertex of the feasible region Corner-point theorem.
Golden-section search reduces the interval each step by a factor of
- 0.5
- 0.618
- 0.382
- 0.9
Show the answer
Answer: B. 0.618 τ.
Lagrange multipliers handle
- equality constraints
- integer variables only
- no constraints
- discontinuities
Show the answer
Answer: A. equality constraints ∇f = λ∇g.
A shadow price tells
- the cost of a product
- the value of one more unit of a constrained resource
- tax
- depreciation
Show the answer
Answer: B. the value of one more unit of a constrained resource Dual value.
Theory questions
A plant makes A (₹40/kg profit) and B (₹30/kg). Steam: 2A + B ≤ 100; labour: A + 2B ≤ 80. Find the best mix. (4 marks)
Show the model answer
Corners: (0,0) 0; (50,0) 2000; (0,40) 1200; intersection 2A + B = 100, A + 2B = 80 ⇒ A = 40, B = 20 ⇒ 1600 + 600 = 2200. Best: 40 kg A and 20 kg B, profit ₹2200.
Explain the golden-section method. (3 marks)
Show the model answer
For a unimodal function on [a, b], evaluate at two interior points placed 0.382 and 0.618 of the way; discard the part beyond the worse point; one old point is reused each step; the interval shrinks by 0.618 per evaluation.
Project scheduling: CPM and PERT
Topics: Network diagrams; activities and events; critical path; float; PERT three-time estimates, expected time and variance; probability of completion; crashing and time–cost trade-off; Gantt charts.
A project network shows activities and their order. A forward pass gives earliest times, a backward pass latest times; activities with zero total float form the critical path, whose length is the project duration. PERT uses optimistic, most likely and pessimistic times: t_e = (a + 4m + b)/6, σ² = ((b − a)/6)². The completion probability uses Z = (T − T_e)/√Σσ² along the critical path. Crashing shortens critical activities at the least cost per day first.
- Total float = LS − ES = LF − EF.
- Critical path has zero float and the longest duration.
- Crash the cheapest critical activity first; watch for new critical paths.
- Gantt charts show schedule against time.
Key formulas
- t_e = (a + 4m + b)/6
- σ² = ((b − a)/6)²
- Z = (T − T_e)/√(Σσ²)
- Float = LS − ES
Practice questions
PERT expected time with a = 2, m = 5, b = 14 is
- 5
- 6
- 7
- 7.5
Show the answer
Answer: B. 6 (2 + 20 + 14)/6.
Activities on the critical path have
- maximum float
- zero float
- negative cost
- no duration
Show the answer
Answer: B. zero float Any delay delays the project.
Crashing means
- cancelling
- shortening activities at extra cost
- adding float
- removing dummies
Show the answer
Answer: B. shortening activities at extra cost Time–cost trade-off.
PERT assumes activity times follow a
- normal
- beta
- uniform
- Poisson
Show the answer
Answer: B. beta Beta distribution.
Theory questions
Activities: A (3 d), B (4 d) after A, C (2 d) after A, D (5 d) after C, E (1 d) after B and D. Find the critical path and duration. (4 marks)
Show the model answer
Paths: A–B–E = 8 d; A–C–D–E = 11 d. Critical path A–C–D–E, 11 days; B has 3 days float.
A critical path has T_e = 40 days and σ² = 16. Find the probability of finishing within 44 days. (3 marks)
Show the model answer
σ = √16 = 4 days. Z = (44 − 40)/4 = 1, and from the normal table P(Z ≤ 1) ≈ 0.84, so there is about an 84 % chance.
Notes, examples and questions were written for this studio; the prescribed books are listed in the studio for reference.
Frequently asked questions
What is the Process Economics & Optimization Studio?
Cost it, judge it, optimise it. Time value of money, capital and manufacturing cost estimation, depreciation, NPV and IRR, break-even, optimum design, linear programming and CPM/PERT.
What can I do in the Process Economics & Optimization Studio?
Interest, annuities and cost indices; Lang factor capital and depreciation; NPV, IRR, payback and break-even; Optimum pipe size, LP and CPM/PERT.
Is the Process Economics & Optimization Studio free?
Yes. It is free and runs in your browser with no sign-up.