Work study, inventory, quality, maintenance and measurement
Topics: Plant layout, work study (method study and time study), production planning, inventory control, CPM and PERT, quality control; maintenance types and lubrication; linear and angular measurement, limits and fits, comparators, screw-thread and surface measurement; drawing, estimating and costing.
Work study, planning and inventory
Work study = method study (find the best way) + work measurement (time it). Normal time = observed time × rating; standard time = normal time × (1 + allowances). Plant layouts: product (line), process (functional), fixed-position and cellular.
Inventory: the economic order quantity EOQ = √(2DS/H) balances ordering cost S against holding cost H for annual demand D.
- Standard time = observed × rating × (1 + allowance)
- EOQ = √(2DS/H)
- Product vs process layout
Example: Observed time 2 min, rating 110 %, allowance 15 %. Find the standard time.
- Normal time = 2 × 1.1 = 2.2 min.
- Standard = 2.2 × 1.15 = 2.53 min.
Answer: 2.53 min
Example: D = 1200 units/year, S = ₹100 per order, H = ₹6 per unit per year. Find the EOQ.
- EOQ = √(2 × 1200 × 100/6).
- = √40 000 = 200 units.
Answer: 200 units
CPM, PERT and quality control
CPM uses fixed activity times and finds the critical path (zero float), which sets the project duration. PERT handles uncertain times with three estimates: t_e = (a + 4m + b)/6 and variance ((b − a)/6)². Quality control uses control charts (x̄ and R for variables, p and c for attributes) with limits at ±3σ, and acceptance sampling.
- t_e = (a + 4m + b)/6
- Variance = ((b − a)/6)²
- Critical path: zero float
Example: An activity has a = 2, m = 4, b = 12 days. Find t_e and its variance.
- t_e = (2 + 16 + 12)/6 = 5 days.
- Variance = (10/6)² ≈ 2.78.
Answer: 5 days; 2.78
Example: What is special about activities on the critical path?
- Any delay in them delays the whole project.
- They have zero float (slack).
Answer: Zero float
Metrology, fits and maintenance
Least count of a vernier = 1 main-scale division − 1 vernier division; a micrometer’s least count = pitch/thimble divisions = 0.5/50 = 0.01 mm. Fits: clearance (always a gap), transition (may be either), interference (always tight). Comparators, slip gauges and sine bars measure precisely.
Maintenance: breakdown (after failure), preventive (scheduled), predictive (based on condition monitoring such as vibration and oil analysis).
- Vernier LC = 1 MSD − 1 VSD
- Micrometer LC = 0.01 mm
- Clearance, transition, interference fits
Example: 10 vernier divisions equal 9 main-scale divisions of 1 mm. Find the least count.
- 1 VSD = 0.9 mm.
- LC = 1 − 0.9 = 0.1 mm.
Answer: 0.1 mm
Work study combines method study (how a job is done, charted with symbols) and time study (how long it takes, with allowances). Product layout suits mass production; process layout suits batches. EOQ = √(2AD/C) balances ordering and holding cost. In CPM the critical path is the longest path through a network and has zero float; PERT uses te = (to + 4tm + tp)/6. Control charts (X̄, R, p, c) monitor quality. Preventive maintenance is scheduled in advance, breakdown maintenance happens after failure. Vernier calipers read to 0.02 mm and micrometers to 0.01 mm. Slip gauges give precise reference lengths, and a sine bar measures angles. The hole-basis system keeps hole size fixed and changes the shaft.
- Fits: clearance, transition, interference.
- ABC analysis: A items are few but high in value.
- Critical path has zero total float.
- Sine bar: sin θ = h/L.
- Selling price = total cost + profit; prime cost = direct material + labour + expenses.
Key formulas
- EOQ = √(2AD/C)
- te = (to + 4tm + tp)/6
- sin θ = h/L
- LC = MSD − VSD
Practice questions
Mass production usually uses
- process layout
- product layout
- fixed layout
- no layout
Show the answer
Answer: B. product layout Line layout.
The critical path is the
- shortest path
- longest path
- cheapest path
- first path
Show the answer
Answer: B. longest path Sets project time.
Expected time in PERT is
- (to + 4tm + tp)/6
- (to + tm + tp)/3
- (to + 2tm + tp)/4
- tm
Show the answer
Answer: A. (to + 4tm + tp)/6 Beta distribution.
ABC analysis is related to
- inventory control
- welding
- casting
- gear design
Show the answer
Answer: A. inventory control Classification by value.
Maintenance done before failure on a schedule is
- breakdown
- preventive
- emergency
- corrective
Show the answer
Answer: B. preventive Planned.
The least count of a metric micrometer is
- 0.1 mm
- 0.02 mm
- 0.01 mm
- 0.001 mm
Show the answer
Answer: C. 0.01 mm Standard.
Slip gauges are used as
- length standards
- hardness testers
- angle generators only
- cutting tools
Show the answer
Answer: A. length standards Reference blocks.
A sine bar measures
- length
- angle
- surface finish
- hardness
Show the answer
Answer: B. angle sin θ = h/L.
A press fit is a
- clearance fit
- interference fit
- transition fit
- loose fit
Show the answer
Answer: B. interference fit Shaft larger than hole.
EOQ balances
- ordering and holding costs
- wages and taxes
- profit and tax
- quality and speed
Show the answer
Answer: A. ordering and holding costs Minimum total cost.
Gantt charts are used to organise
- inventory control
- production schedule
- sales forecasting
- quality control
Show the answer
Answer: B. production schedule
Bin cards help in stores management; queuing theory deals with ____ time.
- waiting
- idle
- inspection
- tool replacement
Show the answer
Answer: A. waiting
In inventory control, the economic order quantity is the
- lot size corresponding to break even analysis.
- average level of inventory.
- optimum lot size.
- none of these.
Show the answer
Answer: C. optimum lot size.
A toy factory has fixed cost Rs. 5000/month, variable cost Rs. 20 per toy and selling price Rs. 30. Its break-even output is ____ toys per month.
- 250
- 500
- 1000
- 3000
Show the answer
Answer: B. 500
In break-even analysis, total cost is fixed cost
- only.
- plus variable cost.
- plus overhead cost.
- plus selling expenses.
Show the answer
Answer: B. plus variable cost.
For income-tax purposes, depreciation of machinery is calculated by the ____ method.
- diminishing balance
- sinking fund
- multiple straight line
- sum of the years digit
Show the answer
Answer: A. diminishing balance
Management is defined as:
- Process of planning, organising, staffing, directing, and controlling to achieve goals
- Only planning
- Only financial control
- Only supervising people
Show the answer
Answer: A. Process of planning, organising, staffing, directing, and controlling to achieve goals
Henri Fayol's 14 principles of management include:
- Division of work, authority and responsibility, unity of command, esprit de corps etc.
- Only 5 principles
- 20 principles
- 10 principles
Show the answer
Answer: A. Division of work, authority and responsibility, unity of command, esprit de corps etc.
Unity of command means:
- Multiple bosses are fine
- None
- Team-based only
- Each employee should receive orders from only one superior
Show the answer
Answer: D. Each employee should receive orders from only one superior
Unity of direction means:
- One head and one plan for a group of activities with the same objective
- Multiple objectives
- None
- Same as unity of command
Show the answer
Answer: A. One head and one plan for a group of activities with the same objective
Scalar chain is:
- Informal communication
- None
- Pay scale
- Line of authority from top management to lowest level
Show the answer
Answer: D. Line of authority from top management to lowest level Line of authority from top management to lowest level (chain of command)
Division of labour (specialisation) leads to:
- Increased efficiency and productivity through specialisation
- Less efficiency
- None
- Boredom only
Show the answer
Answer: A. Increased efficiency and productivity through specialisation
Authority is:
- Accountability
- None
- Right to give orders and make decisions
- Responsibility only
Show the answer
Answer: C. Right to give orders and make decisions
Responsibility is:
- Authority
- None
- Accountability
- Obligation to perform assigned duties
Show the answer
Answer: D. Obligation to perform assigned duties
Accountability is:
- Answerability for the outcome of assigned duties
- Authority
- None
- Responsibility
Show the answer
Answer: A. Answerability for the outcome of assigned duties
Span of control is:
- Number of departments
- Number of levels
- None
- Number of subordinates a manager can effectively supervise
Show the answer
Answer: D. Number of subordinates a manager can effectively supervise
Wide span of control leads to:
- Tall hierarchy
- None
- Flat organisational structure
- More managers
Show the answer
Answer: C. Flat organisational structure Flat organisational structure (fewer management levels)
Narrow span of control leads to:
- None
- Tall organisational structure
- Fewer levels
- Flat structure
Show the answer
Answer: B. Tall organisational structure Tall organisational structure (many management levels)
Line organisation:
- Line and staff
- Direct authority from top to bottom; simplest structure
- Matrix
- None
Show the answer
Answer: B. Direct authority from top to bottom; simplest structure
Line and staff organisation:
- Line only
- Line has authority; staff provides specialist advice
- None
- Matrix
Show the answer
Answer: B. Line has authority; staff provides specialist advice Line has authority; staff provides specialist advice (e.g. HR, legal)
Matrix organisation:
- Employees report to both functional manager and project manager
- Flat only
- Line only
- None
Show the answer
Answer: A. Employees report to both functional manager and project manager Employees report to both functional manager and project manager (dual authority)
Frederick Taylor's Scientific Management:
- None
- One best way to do a job; time and motion studies; differential piece-rate
- Hawthorne studies
- Hierarchy of needs
Show the answer
Answer: B. One best way to do a job; time and motion studies; differential piece-rate
Hawthorne effect (Elton Mayo):
- Only money motivates
- Worker productivity improves when they are observed and feel valued
- None
- Scientific management
Show the answer
Answer: B. Worker productivity improves when they are observed and feel valued Worker productivity improves when they are observed and feel valued (human relations movement)
Maslow's hierarchy of needs (bottom to top):
- Physiological → Safety → Social → Esteem → Self-actualisation
- None
- Only two levels
- Top-down
Show the answer
Answer: A. Physiological → Safety → Social → Esteem → Self-actualisation
Herzberg's two-factor theory:
- Only one factor
- None
- Hygiene factors and motivators
- Only money
Show the answer
Answer: C. Hygiene factors and motivators Hygiene factors (prevent dissatisfaction) and motivators (drive satisfaction)
McGregor's Theory X assumes:
- Workers are lazy, dislike work, need close supervision and control
- Workers are self-directed
- None
- Workers are motivated
Show the answer
Answer: A. Workers are lazy, dislike work, need close supervision and control
McGregor's Theory Y assumes:
- Workers are lazy
- Workers need control
- Workers are self-motivated, creative, seek responsibility under right conditions
- None
Show the answer
Answer: C. Workers are self-motivated, creative, seek responsibility under right conditions
SWOT analysis stands for:
- Strengths, Weaknesses, Opportunities, Threats
- Strategy, Work, Operation, Target
- Survey, Work, Output, Test
- None
Show the answer
Answer: A. Strengths, Weaknesses, Opportunities, Threats
PEST analysis examines:
- Only political
- Only economic
- None
- Political, Economic, Social, Technological factors in external environment
Show the answer
Answer: D. Political, Economic, Social, Technological factors in external environment
MBO (Management by Objectives):
- Manager sets alone
- None
- No objectives
- Manager and employee jointly set objectives; performance reviewed against those objectives
Show the answer
Answer: D. Manager and employee jointly set objectives; performance reviewed against those objectives
Delegation means:
- Removing authority
- Centralising power
- None
- Assigning authority and responsibility to subordinates to perform specific tasks
Show the answer
Answer: D. Assigning authority and responsibility to subordinates to perform specific tasks
Centralisation vs decentralisation:
- Centralisation
- Same thing
- None
- Only large companies differ
Show the answer
Answer: A. Centralisation Centralisation: decisions at top; Decentralisation: decisions pushed down to lower levels
Budgetary control:
- None
- Comparison of actual performance with budgeted figures to identify and correct variances
- Only planning
- Only financial reporting
Show the answer
Answer: B. Comparison of actual performance with budgeted figures to identify and correct variances
Break-even analysis:
- Point where total revenue = total costs; no profit or loss
- Fixed cost calculation
- Only profit calculation
- None
Show the answer
Answer: A. Point where total revenue = total costs; no profit or loss
Break-even point (units) =
- None
- Total costs / price
- Fixed costs /
- Fixed cost / price
Show the answer
Answer: C. Fixed costs / Fixed costs / (selling price per unit − variable cost per unit)
Contribution margin =
- None
- Revenue − total cost
- Selling price − fixed cost
- Selling price − variable cost per unit
Show the answer
Answer: D. Selling price − variable cost per unit
Gantt chart is used for:
- Only resource allocation
- None
- Only financial planning
- Visual scheduling and tracking of project tasks against time
Show the answer
Answer: D. Visual scheduling and tracking of project tasks against time
PERT (Programme Evaluation and Review Technique):
- Only for construction
- Fixed time only
- None
- Network-based technique for projects with uncertain activity times
Show the answer
Answer: D. Network-based technique for projects with uncertain activity times Network-based technique for projects with uncertain activity times (optimistic, most likely, pessimistic)
CPM (Critical Path Method):
- Shortest path
- Identifies the longest path of dependent activities determining project duration
- None
- Any path
Show the answer
Answer: B. Identifies the longest path of dependent activities determining project duration Identifies the longest path of dependent activities (critical path) determining project duration
Critical path activities:
- None
- Activities where any delay directly delays the whole project
- Any activity
- Non-critical activities
Show the answer
Answer: B. Activities where any delay directly delays the whole project Activities where any delay directly delays the whole project (zero float/slack)
Float/slack in project management:
- None
- Time an activity can be delayed without delaying project completion
- Critical path time
- Duration of activity
Show the answer
Answer: B. Time an activity can be delayed without delaying project completion
TQM (Total Quality Management):
- Organisation-wide approach to quality improvement involving all employees and continuous improvement
- Only production
- Only inspection
- None
Show the answer
Answer: A. Organisation-wide approach to quality improvement involving all employees and continuous improvement
Kaizen means:
- None
- Radical change
- Big leap improvement
- Continuous improvement (Japanese concept
Show the answer
Answer: D. Continuous improvement (Japanese concept Continuous improvement (Japanese concept - small incremental improvements daily)
5S methodology:
- 5 resources
- None
- Sort, Set in order, Shine, Standardise, Sustain
- 5 managers
Show the answer
Answer: C. Sort, Set in order, Shine, Standardise, Sustain Sort, Set in order, Shine, Standardise, Sustain - workplace organisation
Six Sigma aims for:
- 3.4 defects per million opportunities
- 6 defects per 100
- Zero defects always
- None
Show the answer
Answer: A. 3.4 defects per million opportunities 3.4 defects per million opportunities (99.9997% quality)
DMAIC in Six Sigma:
- Define, Measure, Analyse, Improve, Control
- None
- Design, Manufacture, Assemble, Inspect, Close
- None of these
Show the answer
Answer: A. Define, Measure, Analyse, Improve, Control Define, Measure, Analyse, Improve, Control - structured problem-solving
ISO 9001 is:
- Environmental standard
- Financial standard
- Safety standard
- International standard for Quality Management Systems
Show the answer
Answer: D. International standard for Quality Management Systems International standard for Quality Management Systems (QMS)
ISO 14001 is:
- Safety standard
- Quality standard
- International standard for Environmental Management Systems
- Financial standard
Show the answer
Answer: C. International standard for Environmental Management Systems International standard for Environmental Management Systems (EMS)
ISO 45001 is:
- Environmental standard
- Financial standard
- Quality standard
- International standard for Occupational Health and Safety management systems
Show the answer
Answer: D. International standard for Occupational Health and Safety management systems International standard for Occupational Health and Safety (OHS) management systems
Supply chain management covers:
- Only manufacturing
- Planning, sourcing, manufacturing, delivery, and returns of products
- Only sourcing
- Only delivery
Show the answer
Answer: B. Planning, sourcing, manufacturing, delivery, and returns of products
JIT (Just-In-Time) inventory:
- Materials arrive exactly when needed
- Weekly replenishment
- Large buffer stocks
- None
Show the answer
Answer: A. Materials arrive exactly when needed Materials arrive exactly when needed - minimises inventory holding costs
EOQ (Economic Order Quantity):
- Minimum order quantity
- Maximum order quantity
- None
- Optimal order quantity minimising total ordering and holding costs
Show the answer
Answer: D. Optimal order quantity minimising total ordering and holding costs Optimal order quantity minimising total ordering and holding costs: EOQ = √(2DS/H)
Human Resource Management (HRM) functions:
- None
- Only payroll
- Only recruitment
- Recruitment, selection, training, performance appraisal, compensation, employee relations
Show the answer
Answer: D. Recruitment, selection, training, performance appraisal, compensation, employee relations
360-degree feedback:
- Only supervisor feedback
- Only self-appraisal
- None
- Feedback from peers, subordinates, supervisors, and self
Show the answer
Answer: D. Feedback from peers, subordinates, supervisors, and self Feedback from peers, subordinates, supervisors, and self - comprehensive performance appraisal
Leadership styles (Lewin):
- None
- Autocratic, Democratic, Laissez-faire
- Four styles only
- Only two styles
Show the answer
Answer: B. Autocratic, Democratic, Laissez-faire Autocratic (directive), Democratic (participative), Laissez-faire (hands-off)
Situational leadership (Hersey-Blanchard):
- None
- Leader adapts style based on follower's maturity/readiness level
- Fixed style
- Only directive
Show the answer
Answer: B. Leader adapts style based on follower's maturity/readiness level
Transformational leadership:
- Transactional only
- Inspires followers to exceed expectations through vision, inspiration, and intellectual stimulation
- Only rewards/punishments
- None
Show the answer
Answer: B. Inspires followers to exceed expectations through vision, inspiration, and intellectual stimulation
Transactional leadership:
- Based on exchange
- Laissez-faire
- None
- Transformational
Show the answer
Answer: A. Based on exchange Based on exchange (rewards for performance, punishment for failure)
Porter's Five Forces:
- PEST analysis
- None
- SWOT analysis
- Competitive rivalry, threat of new entrants, buyer power, supplier power, substitute threat
Show the answer
Answer: D. Competitive rivalry, threat of new entrants, buyer power, supplier power, substitute threat
Value chain analysis (Porter):
- None
- Distribution only
- Supply chain only
- Identifies primary activities and support activities adding value
Show the answer
Answer: D. Identifies primary activities and support activities adding value Identifies primary activities (inbound, operations, outbound, marketing, service) and support activities adding value
Benchmarking is:
- Self-assessment only
- Comparing organisation's performance with best-in-class competitors to identify improvement areas
- Financial comparison only
- None
Show the answer
Answer: B. Comparing organisation's performance with best-in-class competitors to identify improvement areas
Outsourcing means:
- Hiring more employees
- None
- Contracting non-core activities to external specialised providers
- Doing everything in-house
Show the answer
Answer: C. Contracting non-core activities to external specialised providers
Corporate Social Responsibility (CSR):
- Only legal compliance
- Only profit focus
- None
- Company's commitment to social, environmental, and ethical responsibilities beyond profit
Show the answer
Answer: D. Company's commitment to social, environmental, and ethical responsibilities beyond profit
Fayol's principle of Order:
- None
- A place for everything and everything in its place
- Discipline only
- Chain of command
Show the answer
Answer: B. A place for everything and everything in its place A place for everything and everything in its place - material and social order
Fayol's principle of Equity:
- Fairness in pay
- None
- Combination of kindness and justice in dealing with employees
- Equality only
Show the answer
Answer: C. Combination of kindness and justice in dealing with employees
Fayol's principle of Remuneration:
- Low wages always
- High wages always
- Fair wages to employees and employers
- None
Show the answer
Answer: C. Fair wages to employees and employers Fair wages to employees and employers - should be fair and satisfactory
Fayol's principle of Stability of tenure:
- None
- High turnover good
- No stability
- Low employee turnover
Show the answer
Answer: D. Low employee turnover Low employee turnover - time for employee to settle and become productive
Fayol's principle of Initiative:
- No initiative
- Only managers
- None
- Employees should be encouraged to think out and execute plans
Show the answer
Answer: D. Employees should be encouraged to think out and execute plans
Taylor's Differential Piece Rate System:
- Higher rate for workers above standard; lower for below
- Same rate for all
- Only fixed salary
- None
Show the answer
Answer: A. Higher rate for workers above standard; lower for below Higher rate for workers above standard; lower for below - motivates efficiency
Taylor's Planning Department:
- Combined always
- None
- No planning needed
- Separate planning from doing
Show the answer
Answer: D. Separate planning from doing Separate planning from doing - dedicated planners, not foremen
Taylor's Functional Foremanship:
- One foreman only
- 8 specialists instead of one foreman
- No foreman
- None
Show the answer
Answer: B. 8 specialists instead of one foreman 8 specialists (gang boss, speed boss, inspector etc.) instead of one foreman
Gantt Chart inventor:
- Taylor
- None
- Henry Gantt
- Fayol
Show the answer
Answer: C. Henry Gantt Henry Gantt (1917) - bar chart for project scheduling
Gilbreth's Time and Motion Study:
- Frank and Lillian Gilbreth
- Fayol invented
- Taylor invented
- None
Show the answer
Answer: A. Frank and Lillian Gilbreth Frank and Lillian Gilbreth - reduced motions in bricklaying from 18 to 5
Therbligs:
- 17 basic motion elements identified by Gilbreths for time-motion analysis
- Fayol's principles
- Taylor's elements
- None
Show the answer
Answer: A. 17 basic motion elements identified by Gilbreths for time-motion analysis
Bureaucracy theory (Weber):
- Ideal organisation has formal rules, hierarchy, impersonality, merit-based promotion
- Informal only
- Personal relationships
- None
Show the answer
Answer: A. Ideal organisation has formal rules, hierarchy, impersonality, merit-based promotion
Administrative Management vs Scientific Management:
- Same focus
- Fayol focused on top management; Taylor focused on shop floor efficiency
- None
- Taylor focused on top
Show the answer
Answer: B. Fayol focused on top management; Taylor focused on shop floor efficiency
Contingency theory of management:
- One best method
- Classical theory
- No single best management style
- None
Show the answer
Answer: C. No single best management style No single best management style - depends on situation, environment, technology
Systems theory of management:
- Organisation as interrelated parts interacting with environment
- No interaction
- None
- Closed system
Show the answer
Answer: A. Organisation as interrelated parts interacting with environment Organisation as interrelated parts (open system) interacting with environment
Open system vs closed system:
- Closed better
- Open system interacts with environment; closed = no interaction
- None
- Both same
Show the answer
Answer: B. Open system interacts with environment; closed = no interaction Open system interacts with environment (takes inputs, gives outputs); closed = no interaction
Entropy in organisations:
- Order naturally
- No tendency
- None
- Tendency toward disorder and dysfunction
Show the answer
Answer: D. Tendency toward disorder and dysfunction Tendency toward disorder and dysfunction - countered by importing energy/info from environment
Synergy in organisations:
- Combined effect greater than sum of parts
- Impossible
- None
- 2+2=4 always
Show the answer
Answer: A. Combined effect greater than sum of parts Combined effect greater than sum of parts - 2+2=5 in effective organisations
Positive reinforcement in motivation:
- Negative only
- Reward desired behaviour to increase repetition
- Punishment based
- None
Show the answer
Answer: B. Reward desired behaviour to increase repetition Reward desired behaviour to increase repetition (B.F. Skinner's operant conditioning)
Negative reinforcement:
- Positive reinforcement
- Removing unpleasant stimulus when desired behaviour occurs
- None
- Punishment
Show the answer
Answer: B. Removing unpleasant stimulus when desired behaviour occurs Removing unpleasant stimulus when desired behaviour occurs - not punishment
Punishment in behaviour management:
- Extinction
- Positive reinforcement
- Applying unpleasant consequence or removing reward for undesired behaviour
- None
Show the answer
Answer: C. Applying unpleasant consequence or removing reward for undesired behaviour
Extinction:
- None
- Positive reinforcement
- Punishment
- Ignoring undesired behaviour until it disappears
Show the answer
Answer: D. Ignoring undesired behaviour until it disappears Ignoring (not reinforcing) undesired behaviour until it disappears
Expectancy Theory (Vroom):
- None
- Motivation = Expectancy × Instrumentality × Valence
- Hierarchy needs
- Two factor
Show the answer
Answer: B. Motivation = Expectancy × Instrumentality × Valence Motivation = Expectancy × Instrumentality × Valence - rational calculation of effort-reward
Equity Theory (Adams):
- Only recognition
- None
- Motivation affected by perceived fairness
- Only pay
Show the answer
Answer: C. Motivation affected by perceived fairness Motivation affected by perceived fairness - compare input/output ratio to others
Goal-Setting Theory (Locke):
- Specific, challenging goals with feedback increase performance
- Goals reduce motivation
- Vague goals better
- None
Show the answer
Answer: A. Specific, challenging goals with feedback increase performance
ERG Theory (Alderfer):
- 5 levels
- 4 levels
- Existence, Relatedness, Growth
- None
Show the answer
Answer: C. Existence, Relatedness, Growth Existence, Relatedness, Growth - three categories (simpler than Maslow; can regress)
Achievement Motivation Theory (McClelland):
- Only power
- None
- Need for Achievement, Power, Affiliation drive motivation
- Only achievement
Show the answer
Answer: C. Need for Achievement, Power, Affiliation drive motivation Need for Achievement (nAch), Power (nPow), Affiliation (nAff) drive motivation
Transactional vs Transformational leadership:
- Transactional
- Transactional always better
- None
- Same style
Show the answer
Answer: A. Transactional Transactional: exchange-based, rewards/penalties; Transformational: inspires vision and change
Servant leadership:
- Leader controls
- None
- Leader commands
- Leader serves followers' needs
Show the answer
Answer: D. Leader serves followers' needs Leader serves followers' needs - enables them to perform optimally (Robert Greenleaf)
Authentic leadership:
- None
- Being true to one's values, transparent, ethical
- Transactional
- Manipulative
Show the answer
Answer: B. Being true to one's values, transparent, ethical Being true to one's values, transparent, ethical - builds trust and follower identification
Emotional intelligence (EQ) - Goleman's components:
- IQ only
- Technical skills only
- Self-awareness, self-regulation, motivation, empathy, social skills
- None
Show the answer
Answer: C. Self-awareness, self-regulation, motivation, empathy, social skills
Blue Ocean Strategy:
- None
- Create uncontested market space rather than competing in existing markets
- Red ocean competition
- Porter's forces
Show the answer
Answer: B. Create uncontested market space rather than competing in existing markets Create uncontested market space rather than competing in existing markets (Kim & Mauborgne)
Porter's Five Forces:
- Competitive rivalry, supplier power, buyer power, threat of substitutes, threat of new entrants
- None
- Three forces
- Seven forces
Show the answer
Answer: A. Competitive rivalry, supplier power, buyer power, threat of substitutes, threat of new entrants
BCG Matrix categories:
- Four quadrants of risk
- None
- Stars, Cash Cows, Question Marks, Dogs
- Time-based categories
Show the answer
Answer: C. Stars, Cash Cows, Question Marks, Dogs Stars, Cash Cows, Question Marks (Problem Children), Dogs - portfolio management
Ansoff Matrix strategies:
- Three strategies
- Only two strategies
- None
- Market Penetration, Market Development, Product Development, Diversification
Show the answer
Answer: D. Market Penetration, Market Development, Product Development, Diversification
Balanced Scorecard (Kaplan & Norton):
- Only customer
- Only financial
- Four perspectives
- None
Show the answer
Answer: C. Four perspectives Four perspectives: Financial, Customer, Internal Process, Learning & Growth
OKR (Objectives and Key Results):
- Same as KPI
- Only financial goals
- Framework for setting and tracking goals
- None
Show the answer
Answer: C. Framework for setting and tracking goals Framework for setting and tracking goals - used by Google, Intel
KPI (Key Performance Indicator):
- Only qualitative
- None
- Measurable value showing how effectively company is achieving business objectives
- Only financial
Show the answer
Answer: C. Measurable value showing how effectively company is achieving business objectives
Change management - Kotter's 8-step model:
- 5 steps
- Create urgency, build coalition, form vision, communicate, remove obstacles, short-term wins, consolidate, anchor
- 3 steps
- None
Show the answer
Answer: B. Create urgency, build coalition, form vision, communicate, remove obstacles, short-term wins, consolidate, anchor
Lewin's Force Field Analysis:
- Only driving forces
- Driving forces vs restraining forces
- Equal always
- None
Show the answer
Answer: B. Driving forces vs restraining forces Driving forces vs restraining forces - change occurs when driving > restraining
Lewin's Change Model:
- Two stages
- One stage
- Unfreeze → Change → Refreeze
- None
Show the answer
Answer: C. Unfreeze → Change → Refreeze Unfreeze → Change → Refreeze - three-stage model
Project management triple constraint:
- None
- Scope, Time, Cost
- Only time and cost
- Only scope
Show the answer
Answer: B. Scope, Time, Cost Scope, Time, Cost - change one and others are affected
Agile project management:
- Fixed plan only
- None
- Waterfall only
- Iterative, flexible approach
Show the answer
Answer: D. Iterative, flexible approach Iterative, flexible approach - sprints, Scrum, Kanban - for software and complex projects
Waterfall project management:
- Sequential phases
- Scrum
- Agile
- None
Show the answer
Answer: A. Sequential phases Sequential phases (requirements → design → implement → verify → maintain) - rigid but structured
Porter's Generic Strategies:
- [
- C
- o
- "
Show the answer
Answer: A. [
Value Chain Analysis (Porter):
- "
- r
- [
- P
Show the answer
Answer: C. [
Core competence concept (Prahalad & Hamel):
- U
- [
- n
- "
Show the answer
Answer: B. [
Disruptive innovation (Christensen):
- e
- N
- "
- [
Show the answer
Answer: D. [
Jobs-to-be-Done framework:
- u
- C
- [
- "
Show the answer
Answer: C. [
Design Thinking:
- "
- H
- u
- [
Show the answer
Answer: D. [
Lean Startup (Ries):
- "
- u
- [
- B
Show the answer
Answer: C. [
The Business Model Canvas (Osterwalder) consists of how many building blocks?
- 9 blocks
- 7 blocks
- 12 blocks
- 5 blocks
Show the answer
Answer: A. 9 blocks
VUCA (Volatile Uncertain Complex Ambiguous):
- r
- F
- [
- "
Show the answer
Answer: C. [
Organisational learning (Senge - 5th Discipline):
- "
- S
- y
- [
Show the answer
Answer: D. [
Double-loop learning (Argyris):
- u
- Q
- [
- "
Show the answer
Answer: C. [
Knowledge Management - tacit vs explicit:
- T
- "
- [
- a
Show the answer
Answer: C. [
Communities of practice:
- "
- G
- [
- r
Show the answer
Answer: C. [
Supply chain management (SCM):
- C
- "
- [
- o
Show the answer
Answer: C. [
Bullwhip effect in supply chain:
- S
- [
- "
- m
Show the answer
Answer: B. [
VMI (Vendor Managed Inventory):
- S
- "
- u
- [
Show the answer
Answer: D. [
Total Productive Maintenance (TPM) focuses on how many pillars?
- 12 pillars
- 6 pillars
- 8 pillars
- 4 pillars
Show the answer
Answer: C. 8 pillars
OEE (Overall Equipment Effectiveness):
- "
- O
- E
- [
Show the answer
Answer: D. [
World Class Manufacturing (WCM):
- [
- "
- n
- I
Show the answer
Answer: A. [
Production Levelling (Heijunka):
- "
- m
- [
- S
Show the answer
Answer: C. [
Delphi method:
- Only quantitative
- None
- Structured expert consensus technique
- Single expert opinion
Show the answer
Answer: C. Structured expert consensus technique Structured expert consensus technique - iterative questionnaire rounds to forecast or decide
AHP (Analytic Hierarchy Process):
- Multi-criteria decision making
- Single criterion only
- None
- No structure
Show the answer
Answer: A. Multi-criteria decision making Multi-criteria decision making - pairwise comparison of criteria and alternatives (Saaty)
Monte Carlo simulation in management:
- None
- Deterministic only
- Not in management
- Risk analysis by running many random scenarios
Show the answer
Answer: D. Risk analysis by running many random scenarios Risk analysis by running many random scenarios - project cost/schedule risk quantification
Root cause analysis methods:
- Only Pareto
- Only 5-Why
- None
- 5-Why, Fishbone, Fault Tree, FMEA, Pareto
Show the answer
Answer: D. 5-Why, Fishbone, Fault Tree, FMEA, Pareto 5-Why, Fishbone (Ishikawa), Fault Tree, FMEA, Pareto - different depths and approaches
Pareto principle (80-20 rule):
- No such principle
- None
- 80% of effects come from 20% of causes
- 60-40 rule
Show the answer
Answer: C. 80% of effects come from 20% of causes 80% of effects come from 20% of causes - prioritise top 20% for maximum impact
Hoshin Kanri (Policy Deployment):
- a
- J
- "
- [
Show the answer
Answer: D. [
X-matrix in Hoshin Kanri:
- V
- "
- [
- i
Show the answer
Answer: C. [
Theory of Constraints (Goldratt):
- d
- [
- "
- I
Show the answer
Answer: B. [
Drum-Buffer-Rope (DBR):
- O
- [
- "
- T
Show the answer
Answer: B. [
Critical Chain Project Management:
- T
- [
- "
- O
Show the answer
Answer: B. [
Cost of Quality (COQ):
- "
- r
- P
- [
Show the answer
Answer: D. [
Poka-Yoke (mistake proofing):
- "
- D
- [
- e
Show the answer
Answer: C. [
Andon system in manufacturing:
- V
- i
- "
- [
Show the answer
Answer: D. [
Jidoka (autonomation):
- a
- [
- "
- M
Show the answer
Answer: B. [
Takt time:
- v
- [
- A
- "
Show the answer
Answer: B. [
Management by Walking Around (MBWA):
- Avoid shop floor
- None
- Office management only
- Managers regularly walk through workplace, talk to employees
Show the answer
Answer: D. Managers regularly walk through workplace, talk to employees Managers regularly walk through workplace, talk to employees - hands-on leadership style (HP, Toyota)
Open book management:
- None
- Financial secrecy
- Only for executives
- Share financial data with all employees
Show the answer
Answer: D. Share financial data with all employees Share financial data with all employees - creates ownership mentality and alignment with company goals
The practice questions were written for this studio; they are not copied from ASTU papers. ASTU publishes no topic syllabus for these exams, so the topics are an informed guide based on diploma courses, not an official list.